| Action Date | Action Description |
|---|---|
| Mar 29, 2011 | Assent Application Received |
| Mar 29, 2011 | Administrative Review for Completeness |
| Mar 29, 2011 | Team Review for Completeness |
| Mar 29, 2011 | Team Review for Completeness |
| Mar 29, 2011 | Application Accepted |
| Apr 05, 2011 | HPHC Historical Preservation No Effect |
| May 09, 2011 | Biologist Report |
| May 09, 2011 | Engineering Report |
| May 10, 2011 | Typist for Processing |
| May 10, 2011 | Executive Sign Off |
| May 10, 2011 | Sent to Photo Copy |
| May 10, 2011 | Permit Approved |
| Jun 08, 2011 | Land Evidence Date |
| Apr 30, 2014 | Extension of Permit Request |
| Jul 01, 2014 | Extension Toll letter mailed |