| Action Date | Action Description |
|---|---|
| May 30, 2013 | Assent Application Received |
| May 31, 2013 | Administrative Review for Completeness |
| May 31, 2013 | Team Review for Completeness |
| May 31, 2013 | Team Review for Completeness |
| May 31, 2013 | Application Accepted |
| Jul 26, 2013 | Biologist Report |
| Jul 26, 2013 | Engineering Report |
| Jul 26, 2013 | Executive Signoff of Staff Reports |
| Jul 26, 2013 | Category B assigned |
| Jul 31, 2013 | 30 day Public Notice Issued |
| Jul 31, 2013 | Public Notice End Date |
| Jul 31, 2013 | Historical Preservation Conditional Approval |
| Aug 05, 2013 | Mail Agenda Notice |
| Aug 27, 2013 | Semi-Monthly Meeting Postponed |
| Aug 27, 2013 | Ready to Schedule Semi-Monthly Meeting |
| Aug 27, 2013 | Mail Agenda Notice |
| Aug 27, 2013 | Semi-Monthly Meeting Date Scheduled |
| Sep 10, 2013 | Council Approval Granted |
| Sep 10, 2013 | Semi-Monthly Meeting Date Scheduled |
| Sep 10, 2013 | Semi-Monthly Meeting Held |
| Sep 26, 2013 | 30 Day Appeal Notification to Owner |
| Sep 26, 2013 | Stipulation Package from Biologist |
| Sep 26, 2013 | Stipulation Package by Engineer |
| Sep 26, 2013 | Legal Response/Decision |
| Oct 04, 2013 | Permit Approved |
| Oct 04, 2013 | Typist for Processing |
| Oct 07, 2013 | Executive Sign Off |
| Oct 07, 2013 | Sent to Photo Copy |
| Oct 11, 2013 | US Army Corps of Engineers Approval Received |