| Action Date | Action Description |
|---|---|
| Sep 02, 2016 | Assent Application Received |
| Sep 02, 2016 | Administrative Review for Completeness |
| Sep 07, 2016 | Team Review for Completeness |
| Sep 07, 2016 | Application Accepted |
| Sep 19, 2016 | 30 day Public Notice Issued |
| Sep 28, 2016 | HPHC Historical Preservation No Effect |
| Oct 20, 2016 | Public Notice End Date |
| Jan 06, 2017 | Plans Received |
| Feb 07, 2017 | Engineering Report |
| Mar 23, 2017 | Supervisor Engineer SignOff |
| Mar 23, 2017 | Supervisor Biologist SignOff |
| Mar 23, 2017 | Executive Sign Off |
| Aug 23, 2017 | Ready to Schedule Semi-Monthly Meeting |
| Aug 28, 2017 | Mail Agenda Notice |
| Sep 26, 2017 | Semi-Monthly Meeting Unexcused Absence |
| Sep 26, 2017 | Semi-Monthly Meeting Date Scheduled |
| Sep 27, 2017 | Mail Agenda Notice |
| Oct 10, 2017 | Council Approval Granted |
| Oct 10, 2017 | Semi-Monthly Meeting Date Scheduled |
| Oct 10, 2017 | Legal Response/Decision |
| Oct 20, 2017 | Typist for Processing |
| Oct 20, 2017 | Permit Approved |
| Oct 20, 2017 | Stipulation Package by Engineer |
| Oct 31, 2017 | Assent Correction Request Received |
| Oct 31, 2017 | Assent Amended |
| Dec 13, 2017 | Land Evidence Date |