| Action Date | Action Description | 
|---|---|
| Apr 05, 2018 | Assent Application Received | 
| Apr 06, 2018 | Administrative Review for Completeness | 
| Apr 06, 2018 | Team Review for Completeness | 
| Apr 06, 2018 | Application Accepted | 
| Apr 20, 2018 | HPHC Historical Preservation No Effect | 
| May 16, 2018 | Biologist Report | 
| May 16, 2018 | Typist for Processing | 
| May 16, 2018 | Executive Sign Off | 
| May 16, 2018 | Sent to Photo Copy | 
| May 16, 2018 | Permit Approved | 
| Jun 22, 2018 | Land Evidence Date |