| Action Date | Action Description |
|---|---|
| Apr 26, 2019 | Assent Application Received |
| May 06, 2019 | Team Review for Completeness |
| May 06, 2019 | Deficient Application - Owner Notification Sent |
| Jul 16, 2019 | Deficiency Response Received |
| Jul 18, 2019 | Team Review for Completeness |
| Jul 18, 2019 | Application Accepted |
| Aug 13, 2019 | Plans Received |
| Aug 16, 2019 | HPHC Historical Preservation No Effect |
| Aug 16, 2019 | HPHC Review Pending |
| Aug 23, 2019 | Engineering Report |
| Aug 27, 2019 | Typist for Processing |
| Aug 27, 2019 | Executive Sign Off |
| Aug 27, 2019 | Sent to Photo Copy |
| Aug 27, 2019 | Permit Approved |
| Jan 21, 2020 | Land Evidence Date |