| Action Date | Action Description |
|---|---|
| Jun 04, 2020 | Assent Application Received |
| Jun 05, 2020 | Administrative Review for Completeness |
| Jun 05, 2020 | Bio Team Review for Completeness |
| Jun 05, 2020 | Application Accepted |
| Jun 08, 2020 | Project Manager |
| Jun 11, 2020 | HPHC Review Pending |
| Jun 11, 2020 | HPHC Historical Preservation No Effect |
| Jun 29, 2020 | Letter of Authorization for Active File |
| Jul 13, 2020 | Biologist Report |
| Jul 14, 2020 | Typist for Processing |
| Jul 14, 2020 | Executive Sign Off |
| Jul 14, 2020 | Sent to Photo Copy |
| Jul 14, 2020 | Permit Approved |
| Jul 31, 2020 | Land Evidence Date |
| Dec 03, 2020 | Modification Request |
| Dec 03, 2020 | Administrative Review for Completeness |
| Dec 14, 2020 | Bio Team Review for Completeness |
| Dec 15, 2020 | Project Manager |
| Jan 05, 2021 | Biologist Report |
| Jan 05, 2021 | Stipulation Package from Biologist |
| Jan 05, 2021 | Modification Approved |
| Jan 05, 2021 | Typist for Processing |
| Jan 05, 2021 | Executive Sign Off |
| Jan 05, 2021 | Sent to Photo Copy |
| Jan 15, 2021 | Land Evidence Date |
| Jan 21, 2021 | HPHC Historical Preservation No Effect |
| Jan 21, 2021 | HPHC Review Pending |