| Action Date | Action Description |
|---|---|
| Sep 04, 2020 | Federal Consistency Review Request |
| Sep 16, 2020 | Administrative Review for Completeness |
| Sep 17, 2020 | Application Accepted |
| Sep 24, 2020 | Typist for Processing |
| Sep 24, 2020 | Executive Sign Off |
| Sep 24, 2020 | Sent to Photo Copy |
| Sep 24, 2020 | Federal Consistency FMP Concurrence |
| Sep 24, 2020 | Project Manager |
| Sep 24, 2020 | Engineering Report |
| Oct 07, 2020 | HPHC Historical Preservation No Effect |