| Action Date | Action Description |
|---|---|
| Dec 11, 2020 | CHA Worksheet received |
| Dec 11, 2020 | Assent Application Received |
| Dec 14, 2020 | Administrative Review for Completeness |
| Dec 14, 2020 | Bio Team Review for Completeness |
| Dec 14, 2020 | Application Accepted |
| Dec 15, 2020 | Project Manager |
| Jan 21, 2021 | HPHC Historical Preservation No Effect |
| Jan 21, 2021 | HPHC Review Pending |
| Feb 25, 2021 | Stipulation Package from Biologist |
| Feb 25, 2021 | Biologist Report |
| Feb 26, 2021 | Typist for Processing |
| Feb 26, 2021 | Permit Approved |
| Feb 26, 2021 | Executive Sign Off |
| Feb 26, 2021 | Sent to Photo Copy |
| Jun 21, 2021 | Land Evidence Date |
| Dec 15, 2023 | Extension of Permit Request |
| May 17, 2024 | Enforcement Compliance Inspection Required |
| May 17, 2024 | Process Extension |
| May 17, 2024 | Extension Approved |
| Dec 12, 2024 | Extension of Permit Request |
| Jan 13, 2025 | Enforcement Compliance Inspection Required |
| Jan 13, 2025 | Process Extension |
| Jan 14, 2025 | Extension Approved |
| Jan 15, 2025 | Assent Requirement |