| Action Date | Action Description |
|---|---|
| Mar 12, 2021 | Maintenance Certification Request |
| Mar 22, 2021 | Administrative Review for Completeness |
| Mar 22, 2021 | Category A assigned |
| Mar 25, 2021 | Eng Team Review for Completeness |
| Mar 29, 2021 | Application Accepted |
| Mar 31, 2021 | Engineering Report |
| Mar 31, 2021 | Stipulation Package by Engineer |
| Apr 01, 2021 | Typist for Processing |
| Apr 01, 2021 | Permit Approved |
| Apr 01, 2021 | Typist for Processing |
| Apr 14, 2021 | Land Evidence Date |