| Action Date | Action Description |
|---|---|
| Mar 26, 2021 | Assent Application Received |
| Mar 29, 2021 | Administrative Review for Completeness |
| Apr 01, 2021 | Eng Team Review for Completeness |
| Apr 01, 2021 | Application Accepted |
| Apr 01, 2021 | Project Manager |
| May 14, 2021 | Additional Information Received |
| May 19, 2021 | HPHC Historical Preservation No Effect |
| May 19, 2021 | HPHC Review Pending |
| May 20, 2021 | Stipulation Package by Engineer |
| May 20, 2021 | Typist for Processing |
| May 20, 2021 | Engineering Report |
| May 25, 2021 | Permit Approved |
| May 26, 2021 | Assent Correction Request Received |
| May 26, 2021 | Assent Correction Mailed |
| Jun 07, 2021 | Land Evidence Date |