| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 14, 2021 | Assent Application Received |
| May 18, 2021 | Administrative Review for Completeness |
| May 26, 2021 | Eng Team Review for Completeness |
| May 26, 2021 | Application Accepted |
| Jun 03, 2021 | Project Manager |
| Jun 14, 2021 | HPHC Historical Preservation No Effect |
| Jun 14, 2021 | HPHC Review Pending |
| Jul 09, 2021 | Correspondence Received |
| Jul 19, 2021 | Plans Received |
| Jul 26, 2021 | 30 day Public Notice Issued |
| Aug 26, 2021 | Public Notice End Date |
| Sep 15, 2021 | Additional Information Requested from Applicant |
| Sep 15, 2021 | Additional Information Received |
| Sep 20, 2021 | Comments Received |
| Sep 20, 2021 | Comments Received |
| Sep 20, 2021 | Comments Received |
| Sep 27, 2021 | Public Notice End Date Extension Granted |
| Sep 28, 2021 | Objections/Comments Received |
| Jan 04, 2022 | Phone Call |
| Apr 25, 2022 | Additional Information Requested from Applicant |
| May 05, 2022 | Correspondence Received |
| May 05, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jun 09, 2022 | Meeting Held |
| Jun 09, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Sep 19, 2022 | Correspondence Received |
| Sep 19, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Nov 30, 2022 | Correspondence Received |
| Dec 05, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Aug 01, 2023 | 30-Day Notification of Cancellation letter |
| Aug 23, 2023 | Correspondence Received |
| Sep 27, 2023 | Additional Information Received |
| Oct 10, 2023 | Additional Information Requested from Applicant |
| Oct 13, 2023 | Entry of Appearance Received |
| Dec 06, 2023 | 30 day Public Notice Issued |
| Dec 12, 2023 | Mail Agenda Notice |
| Dec 13, 2023 | Plans Received |
| Jan 04, 2024 | Mail Agenda Notice |
| Jan 06, 2024 | Public Notice End Date |
| Jan 08, 2024 | Objections/Comments Received |
| Jan 08, 2024 | Letter of Support for Project |
| Jan 09, 2024 | Continued application |
| Jan 09, 2024 | Semi-Monthly Meeting Date Scheduled |
| Jan 22, 2024 | Biologist Report |
| Jan 22, 2024 | Engineering Report |
| Feb 05, 2024 | Comments Received |
| Feb 13, 2024 | Semimonthly Meeting Cancelled |
| Feb 13, 2024 | Semi-Monthly Meeting Date Scheduled |
| Feb 14, 2024 | Mail Agenda Notice |
| Feb 27, 2024 | Council Approval Granted |
| Feb 27, 2024 | Semi-Monthly Meeting Date Scheduled |
| Nov 07, 2024 | Legal Response/Decision |
| Nov 08, 2024 | Stipulation Package from Biologist |
| Dec 06, 2024 | Typist for Processing |
| Dec 11, 2024 | Executive Sign Off |
| Dec 11, 2024 | Sent to Photo Copy |
| Dec 11, 2024 | Permit Approved |
| Dec 11, 2024 | Permit Mailed |
| Feb 12, 2025 | Land Evidence Date |