| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 24, 2021 | Assent Application Received |
| May 25, 2021 | Administrative Review for Completeness |
| May 27, 2021 | Bio Team Review for Completeness |
| May 27, 2021 | Category B assigned |
| May 28, 2021 | Application Accepted |
| May 28, 2021 | Project Manager |
| May 28, 2021 | Eng Team Review for Completeness |
| Jun 10, 2021 | HPHC Review Pending |
| Jun 10, 2021 | HPHC Historical Preservation No Effect |
| Jul 07, 2021 | Additional Information Received |
| Jul 16, 2021 | 30 day Public Notice Issued |
| Jul 27, 2021 | Additional Information Received |
| Aug 16, 2021 | Public Notice End Date |
| Aug 20, 2021 | Dock Meeting -- Approval |
| Nov 05, 2021 | Plans Received |
| Dec 02, 2021 | Stipulation Package by Engineer |
| Dec 02, 2021 | Engineering Report |
| Dec 03, 2021 | Typist for Processing |
| Dec 03, 2021 | Executive Sign Off |
| Dec 03, 2021 | Sent to Photo Copy |
| Dec 03, 2021 | Permit Approved |
| Dec 07, 2021 | Permit Mailed |
| Dec 13, 2021 | Land Evidence Date |
| Jan 22, 2025 | Additional Information Received |
| Jan 23, 2025 | Modification Request |
| Jan 29, 2025 | Administrative Review for Completeness |
| Jan 31, 2025 | Bio Team Review for Completeness |
| Feb 10, 2025 | Project Manager |
| Feb 10, 2025 | Application Accepted |
| Feb 10, 2025 | Eng Team Review for Completeness |
| Mar 17, 2025 | HPHC Historical Preservation No Effect |
| Mar 19, 2025 | 30 day Public Notice Issued |
| Apr 18, 2025 | Public Notice End Date |
| Jun 11, 2025 | Engineering Report |
| Jun 16, 2025 | Typist for Processing |
| Jun 16, 2025 | Executive Sign Off |
| Jun 16, 2025 | Modification Approved |
| Jun 18, 2025 | Modification mailed |
| Jul 11, 2025 | Land Evidence Date |
| Jul 11, 2025 | Comments Received |
| Jul 11, 2025 | Additional Information Received |
| Jul 11, 2025 | Land Evidence Date |