| Action Date | Action Description |
|---|---|
| Sep 17, 2021 | Assent Application Received |
| Sep 21, 2021 | Administrative Review for Completeness |
| Sep 23, 2021 | Bio Team Review for Completeness |
| Sep 23, 2021 | Application Accepted |
| Sep 23, 2021 | Project Manager |
| Sep 27, 2021 | Additional Information Requested from Applicant |
| Oct 13, 2021 | HPHC Review Pending |
| Oct 13, 2021 | HPHC Historical Preservation No Effect |
| Oct 26, 2021 | Additional Information Received |
| Dec 14, 2021 | Biologist Report |
| Jan 21, 2022 | Typist for Processing |
| Jan 21, 2022 | Executive Sign Off |
| Jan 21, 2022 | Sent to Photo Copy |
| Jan 25, 2022 | Permit Approved |
| Jan 27, 2022 | Permit Mailed |
| Feb 02, 2022 | Land Evidence Date |