| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Sep 29, 2021 | Assent Application Received |
| Oct 05, 2021 | Administrative Review for Completeness |
| Oct 06, 2021 | Bio Team Review for Completeness |
| Oct 06, 2021 | Application Accepted |
| Oct 06, 2021 | Category A* (Docks) |
| Oct 07, 2021 | Project Manager |
| Oct 13, 2021 | HPHC Review Pending |
| Oct 13, 2021 | HPHC Historical Preservation No Effect |
| Nov 23, 2021 | 30 day Public Notice Issued |
| Nov 30, 2021 | US Army Corps of Engineers Approval Received |
| Dec 23, 2021 | Public Notice End Date |
| Jan 11, 2022 | Plans Received |
| Feb 11, 2022 | Dock Meeting -- Approval |
| Feb 16, 2022 | Biologist Report |
| Feb 22, 2022 | Typist for Processing |
| Feb 22, 2022 | Executive Sign Off |
| Feb 22, 2022 | Sent to Photo Copy |
| Feb 22, 2022 | Permit Approved |
| Feb 24, 2022 | Permit Mailed |
| Mar 15, 2022 | Land Evidence Date |