| Action Date | Action Description | 
|---|---|
| Feb 17, 2022 | Maintenance Certification Request | 
| Feb 23, 2022 | Administrative Review for Completeness | 
| Feb 23, 2022 | Bio Team Review for Completeness | 
| Mar 01, 2022 | Bio Team Review for Completeness | 
| Mar 01, 2022 | Application Accepted | 
| Mar 01, 2022 | Project Manager | 
| Mar 24, 2022 | HPHC Review Pending | 
| Mar 24, 2022 | HPHC Historical Preservation No Effect | 
| Apr 29, 2022 | Biologist Report | 
| May 03, 2022 | Typist for Processing | 
| May 03, 2022 | Permit Approved | 
| May 03, 2022 | Executive Sign Off | 
| May 03, 2022 | Sent to Photo Copy | 
| May 05, 2022 | Permit Mailed |