| Action Date | Action Description |
|---|---|
| Apr 27, 2022 | CHA Worksheet received |
| Apr 27, 2022 | Assent Application Received |
| Apr 27, 2022 | Administrative Review for Completeness |
| May 05, 2022 | Bio Team Review for Completeness |
| May 05, 2022 | Application Accepted |
| May 05, 2022 | Project Manager |
| May 25, 2022 | HPHC Historical Preservation No Effect |
| May 25, 2022 | HPHC Review Pending |
| Jun 29, 2022 | Biologist Report |
| Jul 07, 2022 | Typist for Processing |
| Jul 07, 2022 | Executive Sign Off |
| Jul 07, 2022 | Sent to Photo Copy |
| Jul 07, 2022 | Permit Approved |
| Jul 07, 2022 | Permit Mailed |
| Jul 15, 2022 | Land Evidence Date |
| Jun 04, 2025 | Extension of Permit Request |
| Jun 04, 2025 | Modification Request |
| Jun 09, 2025 | Administrative Review for Completeness |
| Jun 11, 2025 | Bio Team Review for Completeness |
| Jun 11, 2025 | Project Manager |
| Jun 11, 2025 | Application Accepted |
| Jun 12, 2025 | Biologist Report |
| Jul 03, 2025 | Typist for Processing |
| Jul 03, 2025 | Executive Sign Off |
| Jul 03, 2025 | Modification Approved |
| Jul 03, 2025 | Modification mailed |
| Jul 10, 2025 | HPHC Historical Preservation No Effect |
| Sep 03, 2025 | Commencement of Work Notice received |