| Action Date | Action Description |
|---|---|
| Oct 20, 2022 | CHA Worksheet received |
| Oct 20, 2022 | Assent Application Received |
| Oct 21, 2022 | Administrative Review for Completeness |
| Oct 21, 2022 | Bio Team Review for Completeness |
| Oct 21, 2022 | Application Accepted |
| Oct 24, 2022 | Project Manager |
| Nov 23, 2022 | Additional Information Requested from Applicant |
| Nov 25, 2022 | HPHC Historical Preservation No Effect |
| Dec 09, 2022 | Additional Information Received |
| Dec 13, 2022 | Plans Received |
| Dec 13, 2022 | Biologist Report |
| Dec 14, 2022 | Typist for Processing |
| Dec 14, 2022 | Executive Sign Off |
| Dec 14, 2022 | Sent to Photo Copy |
| Dec 14, 2022 | Permit Approved |
| Dec 15, 2022 | Permit Mailed |
| Dec 16, 2022 | Land Evidence Date |