| Action Date | Action Description |
|---|---|
| Assent Requirement | |
| Apr 21, 2023 | Assent Application Received |
| Apr 21, 2023 | CHA Worksheet received |
| Apr 28, 2023 | Application Accepted |
| Apr 28, 2023 | Project Manager |
| Apr 28, 2023 | Administrative Review for Completeness |
| Apr 28, 2023 | Bio Team Review for Completeness |
| May 30, 2023 | HPHC Historical Preservation No Effect |
| Feb 16, 2024 | Plans Received |
| Mar 04, 2024 | Additional Information Received |
| Mar 28, 2024 | Additional Information Received |
| May 06, 2024 | Plans Received |
| May 14, 2024 | Typist for Processing |
| May 14, 2024 | Executive Sign Off |
| May 14, 2024 | Sent to Photo Copy |
| May 14, 2024 | Permit Approved |
| May 14, 2024 | Biologist Report |
| May 17, 2024 | Permit Mailed |
| Jun 07, 2024 | Land Evidence Date |
| Jan 17, 2025 | Additional Information Received |