| Action Date | Action Description |
|---|---|
| Feb 04, 2005 | Assent Application Received |
| Feb 07, 2005 | Administrative Review for Completeness |
| Feb 08, 2005 | Application Accepted |
| Feb 16, 2005 | Deficient Application - Owner Notification Sent |
| Feb 22, 2005 | Correspondence Received |
| Feb 22, 2005 | Correspondence Received |
| Feb 24, 2005 | Deficiency Response Received |
| Mar 14, 2005 | Plans Received |
| Apr 19, 2005 | Application Cancelled |
| Apr 19, 2005 | Team Review for Completeness |