| Action Date | Action Description |
|---|---|
| Jul 27, 2005 | Assent Application Received |
| Jul 28, 2005 | Administrative Review for Completeness |
| Aug 04, 2005 | Team Review for Completeness |
| Aug 04, 2005 | Application Accepted |
| Aug 04, 2005 | Category A* (Docks) |
| Aug 26, 2005 | HPHC Review Pending |
| Sep 02, 2005 | 30 day Public Notice Issued |
| Oct 02, 2005 | Public Notice End Date |
| Oct 17, 2005 | Biologist Report |
| Oct 17, 2005 | Engineering Report |
| Oct 18, 2005 | Dock Meeting Scheduled (Admin) |
| Oct 24, 2005 | US Army Corp of Engineers Permit Date |
| Oct 26, 2005 | US Army Corps of Engineers Approval Received |
| Oct 28, 2005 | Dock sub-committee Approved |
| Feb 06, 2006 | Typist for Processing |
| Feb 06, 2006 | Executive Sign Off |
| Feb 06, 2006 | Sent to Photo Copy |
| Feb 06, 2006 | Permit Approved |
| Mar 01, 2006 | Land Evidence Date |