| Action Date | Action Description |
|---|---|
| Jan 06, 2006 | Assent Application Received |
| Jan 06, 2006 | Administrative Review for Completeness |
| Feb 15, 2006 | Deficient Application - Owner Notification Sent |
| Feb 22, 2006 | Deficient Application Picked Up |
| Apr 14, 2006 | Deficiency Response Received |
| Apr 26, 2006 | Team Review for Completeness |
| Apr 26, 2006 | Application Accepted |
| May 12, 2006 | HPHC Historical Preservation No Effect |
| May 25, 2006 | Additional Information Requested from Applicant |
| Jun 20, 2006 | Additional Information Received |
| Jul 12, 2006 | Typist for Processing |
| Jul 12, 2006 | Executive Sign Off |
| Jul 12, 2006 | Sent to Photo Copy |
| Jul 12, 2006 | Permit Approved |
| Jul 12, 2006 | Biologist Report |
| Aug 02, 2006 | Land Evidence Date |
| Oct 23, 2006 | Commencement of Work Notice received |
| Jul 25, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Aug 30, 2007 | Additional Information Received |
| Oct 10, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Oct 23, 2007 | Conservation Easement Recording received |
| Nov 01, 2007 | Modification Request |
| Nov 02, 2007 | Administrative Review for Completeness |
| Nov 26, 2007 | Team Review for Completeness |
| Nov 26, 2007 | Team Review for Completeness |
| Dec 07, 2007 | HPHC Historical Preservation No Effect |
| Apr 03, 2008 | Additional Information Received |
| Apr 21, 2008 | Engineering Report |
| Apr 21, 2008 | Biologist Report |
| Apr 22, 2008 | Typist for Processing |
| Apr 22, 2008 | Executive Sign Off |
| Apr 22, 2008 | Sent to Photo Copy |
| Apr 22, 2008 | Modification Approved |
| Apr 29, 2008 | Land Evidence Date |