| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| Nov 26, 2008 | Assent Application Received |
| Dec 01, 2008 | Administrative Review for Completeness |
| Dec 02, 2008 | Team Review for Completeness |
| Dec 02, 2008 | Team Review for Completeness |
| Dec 02, 2008 | Application Accepted |
| Dec 05, 2008 | Biologist Report |
| Dec 08, 2008 | Typist for Processing |
| Dec 08, 2008 | Executive Sign Off |
| Dec 08, 2008 | Sent to Photo Copy |
| Dec 08, 2008 | Permit Approved |
| Dec 22, 2008 | HPHC Historical Preservation No Effect |
| Dec 31, 2008 | Letter of Authorization |
| Feb 03, 2009 | Land Evidence Date |
| Apr 21, 2009 | Modification Request |
| Apr 22, 2009 | Administrative Review for Completeness |
| Apr 27, 2009 | Team Review for Completeness |
| Apr 27, 2009 | Team Review for Completeness |
| Apr 27, 2009 | Biologist Report |
| Apr 27, 2009 | Engineering Report |
| Apr 28, 2009 | Modification Approved |
| May 14, 2009 | HPHC Historical Preservation No Effect |
| May 21, 2009 | Land Evidence Date |
| Jun 08, 2009 | Letter of Authorization |
| Jun 23, 2009 | Modification Request |
| Jun 25, 2009 | Administrative Review for Completeness |
| Jun 25, 2009 | Team Review for Completeness |
| Jun 25, 2009 | Team Review for Completeness |
| Jun 29, 2009 | Biologist Report |
| Jun 29, 2009 | Engineering Report |
| Jun 29, 2009 | Typist for Processing |
| Jun 29, 2009 | Executive Sign Off |
| Jun 29, 2009 | Sent to Photo Copy |
| Jun 29, 2009 | Modification Approved |
| Jul 14, 2009 | Correspondence Received |
| Jul 20, 2009 | HPHC Historical Preservation No Effect |
| Jul 22, 2009 | Land Evidence Date |
| Jul 30, 2009 | Additional Information Received |
| Jul 31, 2009 | Correspondence Received |
| Apr 27, 2010 | Additional Information Received |
| Apr 30, 2010 | Letter of Authorization |
| Feb 03, 2011 | HPHC Historical Preservation No Effect |
| Feb 21, 2011 | Modification Request |
| Feb 21, 2011 | Administrative Review for Completeness |
| Feb 21, 2011 | Team Review for Completeness |
| Feb 21, 2011 | Team Review for Completeness |
| Feb 22, 2011 | Executive Sign Off |
| Feb 22, 2011 | Sent to Photo Copy |
| Feb 22, 2011 | Modification Approved |
| Feb 24, 2011 | Biologist Report |
| Feb 25, 2011 | Typist for Processing |
| Mar 22, 2011 | Land Evidence Date |
| Apr 05, 2011 | Commencement of Work Notice received |
| Sep 13, 2011 | RIDEM Approval required |
| Jan 30, 2012 | RIDEM Approval required |
| Jan 30, 2012 | Monitoring Report |
| Feb 02, 2012 | Letter of Authorization |
| Feb 06, 2012 | Additional Information Received |
| Feb 06, 2012 | Monitoring Report |
| Apr 23, 2012 | Monitoring Report |
| Apr 23, 2012 | Additional Information Received |
| Apr 26, 2012 | Additional Information Received |
| Apr 26, 2012 | Modification Request |
| May 02, 2012 | Team Review for Completeness |
| May 08, 2012 | Biologist Report |
| May 08, 2012 | Letter of Authorization |
| May 09, 2012 | Monitoring Report |
| Dec 20, 2013 | Correspondence Received |
| Mar 20, 2015 | Correspondence Received |
| May 05, 2016 | Modification Request |
| May 07, 2016 | Administrative Review for Completeness |
| May 16, 2016 | Team Review for Completeness |
| May 17, 2016 | Engineering Report |
| May 18, 2016 | Typist for Processing |
| May 23, 2016 | Executive Sign Off |
| May 23, 2016 | Sent to Photo Copy |
| May 23, 2016 | Modification Approved |
| May 23, 2016 | HPHC Historical Preservation No Effect |
| May 23, 2016 | HPHC Historical Preservation No Effect |
| Jun 14, 2016 | Land Evidence Date |