| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 18, 2010 | Assent Application Received |
| May 19, 2010 | Administrative Review for Completeness |
| May 19, 2010 | Team Review for Completeness |
| May 19, 2010 | Team Review for Completeness |
| May 19, 2010 | Application Accepted |
| May 20, 2010 | 30 day Public Notice Issued |
| Jun 14, 2010 | Correspondence Received |
| Jun 16, 2010 | Correspondence Received |
| Jun 20, 2010 | Public Notice End Date |
| Jun 24, 2010 | HPHC Historical Preservation No Effect |
| Jul 13, 2010 | Biologist Report |
| Jul 13, 2010 | Engineering Report |
| Jul 13, 2010 | Objections/Comments Received |
| Jul 15, 2010 | Correspondence Received |
| Jul 16, 2010 | Entry of Appearance Received |
| Jul 16, 2010 | Correspondence Received |
| Jul 16, 2010 | Public Notice End Date Extension Granted |
| Jul 16, 2010 | Objections/Comments Received |
| Jul 16, 2010 | Objection withdrawal received |
| Jul 20, 2010 | Objections/Comments Received |
| Jul 22, 2010 | US Army Corp of Engineers Permit Date |
| Jul 28, 2010 | Executive Signoff of Staff Reports |
| Aug 05, 2010 | Objections/Comments Received |
| Sep 16, 2010 | Objections/Comments Received |
| Sep 30, 2010 | Correspondence Received |
| Aug 02, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Aug 03, 2011 | Correspondence Received |
| Aug 05, 2011 | Continuance Requested |
| Aug 09, 2011 | Continuance request by objector granted by Council |
| Aug 23, 2011 | Semi-Monthly Meeting Date Scheduled |
| Sep 06, 2011 | Prehearing Conference |
| Sep 12, 2011 | Correspondence Mailed/Faxed/E-mailed |
| Nov 04, 2011 | Additional Information Received |
| Nov 04, 2011 | Objections/Comments Received |
| Nov 15, 2011 | Mail Agenda Notice |
| Nov 22, 2011 | Continuance Requested |
| Nov 22, 2011 | Continuance request by applicant granted by Council |
| Nov 22, 2011 | Semi-Monthly Meeting Date Scheduled |
| Dec 21, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Dec 21, 2011 | Mail Agenda Notice |
| Jan 24, 2012 | Semi-Monthly Meeting Held |
| Jan 24, 2012 | Semi-Monthly Meeting Date Scheduled |
| Jan 24, 2012 | Continued Application by the Council |
| Jan 25, 2012 | Mail Agenda Notice |
| Jan 25, 2012 | Ready to Schedule Semi-Monthly Meeting |
| Feb 14, 2012 | Semi-Monthly Meeting Held |
| Feb 14, 2012 | Semi-Monthly Meeting Date Scheduled |
| Feb 27, 2012 | Correspondence Received |
| Mar 29, 2012 | Sub-Committee Members Assigned |
| Apr 16, 2012 | Public Hearing Scheduled |
| Apr 19, 2012 | Correspondence Received |
| May 09, 2012 | Correspondence Received |
| May 31, 2012 | Additional Information Received |
| May 31, 2012 | Objections/Comments Received |
| Jun 05, 2012 | Public Hearing Held |
| Jun 08, 2012 | Public Hearing Notices Mailed |
| Jun 19, 2012 | Public Hearing Scheduled |
| Jun 26, 2012 | Public Hearing Notices Mailed |
| Jul 18, 2012 | Public Hearing Scheduled |
| Jul 24, 2012 | Public Hearing Notices Mailed |
| Aug 22, 2012 | Public Hearing Scheduled |
| Sep 12, 2012 | Public Hearing Scheduled |
| Sep 19, 2012 | Public Hearing Notices Mailed |
| Oct 15, 2012 | Public Hearing Workshop Postponed |
| Oct 15, 2012 | Public Hearing Workshop Scheduled |
| Oct 24, 2012 | Public Hearing Notices Mailed |
| Nov 15, 2012 | Public Hearing Workshop Scheduled |
| Feb 12, 2013 | Sub-Committee Report To Full Council |
| Mar 29, 2013 | Ready to Schedule Semi-Monthly Meeting |
| Mar 29, 2013 | Mail Agenda Notice |
| Apr 02, 2013 | Mail Agenda Notice |
| Apr 04, 2013 | Correspondence Received |
| Apr 08, 2013 | Mail Agenda Notice |
| Apr 09, 2013 | Continued Application by the Council |
| Apr 09, 2013 | Semi-Monthly Meeting Date Scheduled |
| May 13, 2013 | Correspondence Received |
| May 14, 2013 | Semi-Monthly Meeting Held |
| May 14, 2013 | Council Approval Granted |
| May 14, 2013 | Semi-Monthly Meeting Date Scheduled |
| Sep 09, 2013 | Legal Response/Decision |
| Sep 10, 2013 | 30 Day Appeal Notification to Owner |
| Oct 03, 2013 | Plans Received |
| Apr 24, 2025 | 30 day Public Notice Issued |
| May 15, 2025 | Entry of Appearance Received |
| May 26, 2025 | Public Notice End Date |
| Jul 02, 2025 | Stipulation Package by Engineer |
| Jul 03, 2025 | Typist for Processing |
| Jul 03, 2025 | Executive Sign Off |
| Jul 03, 2025 | Permit Approved |
| Jul 03, 2025 | Permit Mailed |
| Jul 10, 2025 | Land Evidence Date |