| Action Date | Action Description |
|---|---|
| Jul 02, 2012 | Assent Application Received |
| Jul 03, 2012 | Administrative Review for Completeness |
| Aug 01, 2012 | Team Review for Completeness |
| Aug 01, 2012 | Team Review for Completeness |
| Aug 01, 2012 | Application Accepted |
| Aug 20, 2012 | 30 day Public Notice Issued |
| Aug 20, 2012 | Public Notice End Date |
| Sep 01, 2012 | HPHC Historical Preservation No Effect |
| Sep 27, 2012 | Additional Information Received |
| Oct 15, 2012 | Correspondence Received |
| Oct 17, 2012 | Additional Information Received |
| Oct 24, 2012 | Biologist Report |
| Oct 24, 2012 | Engineering Report |
| Oct 31, 2012 | Supervisor Biologist SignOff |
| Oct 31, 2012 | Supervisor Engineer SignOff |
| Nov 01, 2012 | Executive Signoff of Staff Reports |
| Nov 20, 2012 | Ready to Schedule Semi-Monthly Meeting |
| Nov 26, 2012 | US Army Corps of Engineers Approval Received |
| Nov 27, 2012 | Semi-Monthly Meeting Held |
| Nov 27, 2012 | Council Approval Granted |
| Nov 27, 2012 | Semi-Monthly Meeting Date Scheduled |
| Nov 27, 2012 | Mail Agenda Notice |
| Dec 11, 2012 | Legal Response/Decision |
| Dec 11, 2012 | 30 Day Appeal Notification to Owner |
| Dec 12, 2012 | Stipulation Package from Biologist |
| Dec 12, 2012 | Stipulation Package by Engineer |
| Dec 19, 2012 | Typist for Processing |
| Dec 19, 2012 | Executive Sign Off |
| Dec 19, 2012 | Sent to Photo Copy |
| Dec 19, 2012 | Permit Approved |
| Jan 04, 2013 | Duplicate Original Assent requested/mailed |
| Jan 18, 2013 | Land Evidence Date |
| Jan 31, 2013 | RIPDES Permit Issued |