| Action Date | Action Description |
|---|---|
| May 08, 2015 | Assent Application Received |
| May 08, 2015 | Administrative Review for Completeness |
| May 11, 2015 | Correspondence Received |
| May 13, 2015 | Application Accepted |
| May 13, 2015 | Team Review for Completeness |
| Jun 23, 2015 | 30 day Public Notice Issued |
| Jul 08, 2015 | Meeting Held |
| Jul 09, 2015 | Objections/Comments Received |
| Jul 15, 2015 | Correspondence Mailed/Faxed/E-mailed |
| Jul 23, 2015 | Public Notice End Date |
| Jul 24, 2015 | Correspondence Received |
| Aug 31, 2015 | Plans Received |
| Oct 09, 2015 | Plans Received |
| Nov 16, 2015 | Mail Agenda Notice |
| Nov 16, 2015 | Meeting Held |
| Nov 25, 2015 | Plans Received |
| Dec 01, 2015 | Biologist Report |
| Dec 01, 2015 | Engineering Report |
| Dec 02, 2015 | Supervisor Engineer SignOff |
| Dec 02, 2015 | Executive Signoff of Staff Reports |
| Dec 03, 2015 | Water Quality Certification |
| Dec 08, 2015 | Council Approval Granted |
| Dec 08, 2015 | Semi-Monthly Meeting Date Scheduled |
| Jan 12, 2016 | Legal Response/Decision |
| Jan 12, 2016 | 30 Day Appeal Notification to Owner |
| Mar 03, 2016 | Correspondence Received |
| Mar 10, 2016 | Stipulation Package from Biologist |
| Mar 10, 2016 | Stipulation Package by Engineer |
| Mar 31, 2016 | Correspondence Received |
| Apr 22, 2016 | Typist for Processing |
| Apr 25, 2016 | Executive Sign Off |
| Apr 25, 2016 | Sent to Photo Copy |
| Apr 25, 2016 | Permit Approved |
| May 02, 2016 | Conservation Easement and Restrictions Requested |
| May 05, 2016 | Land Evidence Date |
| Jul 05, 2017 | Plans Received |
| Jul 17, 2017 | Correspondence Received |
| Aug 25, 2017 | Modification Request |
| Aug 25, 2017 | Administrative Review for Completeness |
| Aug 29, 2017 | Team Review for Completeness |
| Aug 29, 2017 | Application Accepted |
| Sep 13, 2017 | HPHC Historical Preservation No Effect |
| Oct 13, 2017 | Plans Received |
| Nov 15, 2017 | Plans Received |
| Nov 20, 2017 | Additional Information Received |
| Dec 08, 2017 | Modification Approved |
| Dec 08, 2017 | Biologist Report |
| Dec 08, 2017 | Engineering Report |
| Mar 09, 2018 | Land Evidence Date |
| Apr 18, 2018 | Modification Request |
| Apr 18, 2018 | Administrative Review for Completeness |
| Apr 26, 2018 | HPHC Historical Preservation No Effect |
| Apr 26, 2018 | Team Review for Completeness |
| Apr 26, 2018 | Application Accepted |
| May 25, 2018 | Biologist Report |
| May 25, 2018 | Engineering Report |
| May 29, 2018 | Expiration of Assent/End of Tolling Legislation |
| May 29, 2018 | Typist for Processing |
| May 29, 2018 | Executive Sign Off |
| May 29, 2018 | Sent to Photo Copy |
| May 29, 2018 | Modification Approved |
| May 29, 2018 | Permit Approved |
| Jun 12, 2018 | HPHC Historical Preservation Comments/Concerns |
| Jun 15, 2018 | Land Evidence Date |
| Aug 30, 2018 | Note to File |
| Mar 05, 2019 | Note to File |
| Jun 10, 2019 | Additional Information Received |