| Action Date | Action Description |
|---|---|
| Dec 10, 2018 | Assent Application Received |
| Dec 10, 2018 | Administrative Review for Completeness |
| Jan 04, 2019 | Team Review for Completeness |
| Jan 04, 2019 | Application Accepted |
| Jan 24, 2019 | HPHC Review Pending |
| Jan 24, 2019 | HPHC Historical Preservation No Effect |
| Jan 28, 2019 | Plans Received |
| Feb 08, 2019 | Typist for Processing |
| Feb 08, 2019 | Permit Approved |
| Feb 08, 2019 | Engineering Report |
| Feb 20, 2019 | HPHC Historical Preservation No Effect |