| Action Date | Action Description |
|---|---|
| Dec 14, 2018 | Assent Application Received |
| Dec 14, 2018 | Application Accepted |
| Dec 14, 2018 | Engineering Report |
| Dec 14, 2018 | Finding of No Significant Impact-OTC |
| Sep 20, 2021 | Extension of Permit Request |
| Feb 10, 2022 | Enforcement Compliance Inspection Required |
| Feb 22, 2022 | Process Extension |
| Feb 22, 2022 | Extension Approved |
| Nov 18, 2022 | Extension of Permit Request |
| May 08, 2023 | Enforcement Compliance Inspection Required |
| May 11, 2023 | Process Extension |
| May 11, 2023 | Extension Approved |
| Dec 01, 2023 | Extension of Permit Request |
| Feb 06, 2024 | Enforcement Compliance Inspection Required |
| Apr 12, 2024 | Process Extension |