| Action Date | Action Description |
|---|---|
| Jul 01, 2019 | Team Review for Completeness |
| Jul 01, 2019 | Application Accepted |
| Jul 01, 2019 | Assent Application Received |
| Jul 01, 2019 | Administrative Review for Completeness |
| Jul 02, 2019 | Entry of Appearance Received |
| Jul 19, 2019 | HPHC Historical Preservation Comments/Concerns |
| Aug 01, 2019 | Correspondence Mailed/Faxed/E-mailed |
| Aug 29, 2019 | HPHC Historical Preservation No Effect |
| Aug 29, 2019 | HPHC Review Pending |
| Oct 15, 2019 | Additional Information Received |
| Nov 01, 2019 | Plans Received |
| Nov 07, 2019 | Plans Received |
| Nov 13, 2019 | 30 day Public Notice Issued |
| Dec 12, 2019 | Objections/Comments Received |
| Dec 13, 2019 | Public Notice End Date |
| Dec 23, 2019 | Objections/Comments Received |
| Jan 06, 2020 | Correspondence Received |
| Jan 09, 2020 | Comments Received |
| Feb 07, 2020 | Correspondence Received |
| Mar 11, 2020 | Biologist Report |
| Mar 19, 2020 | Engineering Report |
| Mar 24, 2020 | Executive Signoff of Staff Reports |
| Mar 08, 2022 | Application Cancelled |