| Action Date | Action Description |
|---|---|
| Sep 21, 2020 | Assent Application Received |
| Sep 23, 2020 | Administrative Review for Completeness |
| Oct 09, 2020 | Bio Team Review for Completeness |
| Oct 09, 2020 | Deficient Application - Owner Notification Sent |
| Oct 07, 2021 | Deficiency Response Received |
| Oct 20, 2021 | Bio Team Review for Completeness |
| Oct 20, 2021 | Application Accepted |
| Oct 20, 2021 | Project Manager |
| Oct 26, 2021 | Additional Information Requested from Applicant |
| Nov 02, 2021 | HPHC Historical Preservation No Effect |
| Nov 02, 2021 | HPHC Review Pending |
| Mar 30, 2022 | 30-Day Notification of Cancellation letter |
| May 23, 2022 | Additional Information Received |
| Jul 08, 2022 | Biologist Report |
| Jul 15, 2022 | Permit Mailed |
| Jul 15, 2022 | Typist for Processing |
| Jul 15, 2022 | Executive Sign Off |
| Jul 15, 2022 | Sent to Photo Copy |
| Jul 15, 2022 | Permit Approved |
| Jul 22, 2022 | Phone Call |
| Jul 22, 2022 | Note to File |
| Aug 16, 2022 | Land Evidence Date |