| Action Date | Action Description |
|---|---|
| Biologist Report | |
| Jul 12, 2021 | Assent Application Received |
| Jul 13, 2021 | Administrative Review for Completeness |
| Jul 13, 2021 | CHA Worksheet received |
| Jul 19, 2021 | Bio Team Review for Completeness |
| Jul 20, 2021 | Application Accepted |
| Jul 20, 2021 | Project Manager |
| Jul 30, 2021 | Biologist Report |
| Jul 30, 2021 | Stipulation Package from Biologist |
| Aug 05, 2021 | Typist for Processing |
| Aug 05, 2021 | Executive Sign Off |
| Aug 05, 2021 | Sent to Photo Copy |
| Aug 05, 2021 | Permit Approved |
| Aug 05, 2021 | HPHC Review Pending |
| Aug 05, 2021 | HPHC Historical Preservation No Effect |
| Aug 19, 2021 | Permit Mailed |
| Aug 26, 2021 | Commencement of Work Notice received |
| Sep 07, 2021 | Land Evidence Date |