| Action Date | Action Description |
|---|---|
| Jul 23, 2021 | Assent Application Received |
| Jul 26, 2021 | Administrative Review for Completeness |
| Jul 26, 2021 | CHA Worksheet received |
| Jul 27, 2021 | Bio Team Review for Completeness |
| Jul 27, 2021 | Application Accepted |
| Jul 28, 2021 | Project Manager |
| Aug 20, 2021 | HPHC Historical Preservation No Effect |
| Aug 20, 2021 | HPHC Review Pending |
| Sep 07, 2021 | Additional Information Requested from Applicant |
| Jan 12, 2022 | Plans Received |
| Feb 18, 2022 | Biologist Report |
| Feb 23, 2022 | Typist for Processing |
| Feb 23, 2022 | Executive Sign Off |
| Feb 23, 2022 | Sent to Photo Copy |
| Feb 23, 2022 | Permit Approved |
| Feb 28, 2022 | Permit Mailed |
| Mar 16, 2022 | Land Evidence Date |
| Jan 21, 2025 | Modification Request |
| Jan 27, 2025 | Administrative Review for Completeness |
| Jan 31, 2025 | Bio Team Review for Completeness |
| Jan 31, 2025 | Project Manager |
| Jan 31, 2025 | Application Accepted |
| Feb 25, 2025 | HPHC Historical Preservation No Effect |
| Feb 27, 2025 | Biologist Report |
| Mar 04, 2025 | Typist for Processing |
| Mar 04, 2025 | Executive Sign Off |
| Mar 04, 2025 | Sent to Photo Copy |
| Mar 04, 2025 | Note to File |
| Mar 04, 2025 | Modification Approved |
| Mar 04, 2025 | Modification mailed |
| Mar 05, 2025 | Extension of Permit Request |
| Mar 05, 2025 | Enforcement Compliance Inspection Required |
| Apr 10, 2025 | Land Evidence Date |