| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 06, 2021 | Assent Application Received |
| Dec 09, 2021 | Administrative Review for Completeness |
| Dec 09, 2021 | Category A* (Docks) |
| Feb 08, 2022 | Bio Team Review for Completeness |
| Feb 14, 2022 | Deficient Application - Owner Notification Sent |
| May 27, 2022 | Deficiency Response Received |
| Jun 07, 2022 | Bio Team Review for Completeness |
| Jun 07, 2022 | Application Accepted |
| Jun 10, 2022 | Project Manager |
| Jun 21, 2022 | HPHC Review Pending |
| Jun 21, 2022 | HPHC Historical Preservation No Effect |
| Jun 29, 2022 | 30 day Public Notice Issued |
| Jul 01, 2022 | US Army Corps of Engineers Approval Received |
| Jul 29, 2022 | Public Notice End Date |
| Aug 17, 2022 | Dock Meeting -- Approval |
| Aug 19, 2022 | Biologist Report |
| Aug 23, 2022 | Typist for Processing |
| Aug 23, 2022 | Executive Sign Off |
| Aug 23, 2022 | Sent to Photo Copy |
| Aug 23, 2022 | Permit Approved |
| Aug 23, 2022 | Permit Mailed |
| Jan 11, 2023 | Land Evidence Date |