| Action Date | Action Description |
|---|---|
| Mar 22, 2022 | Maintenance Certification Request |
| Mar 25, 2022 | Administrative Review for Completeness |
| Apr 07, 2022 | Eng Team Review for Completeness |
| Apr 07, 2022 | Deficient Application - Owner Notification Sent |
| Apr 26, 2022 | Deficiency Response Received |
| May 09, 2022 | Eng Team Review for Completeness |
| May 09, 2022 | Application Accepted |
| May 10, 2022 | Project Manager |
| May 16, 2022 | Engineering Report |
| May 17, 2022 | HPHC Historical Preservation No Effect |
| May 18, 2022 | Permit Approved |
| May 19, 2022 | Permit Mailed |