| Action Date | Action Description |
|---|---|
| Apr 04, 2022 | Assent Application Received |
| Apr 06, 2022 | Administrative Review for Completeness |
| Apr 07, 2022 | Bio Team Review for Completeness |
| Apr 07, 2022 | Application Accepted |
| Apr 07, 2022 | Project Manager |
| Apr 07, 2022 | Category A* (Docks) |
| Apr 19, 2022 | 30 day Public Notice Issued |
| Apr 20, 2022 | Comments Received |
| May 06, 2022 | HPHC Historical Preservation No Effect |
| May 19, 2022 | Public Notice End Date |
| Jun 09, 2022 | Dock Meeting -- Approval |
| Jun 13, 2022 | Biologist Report |
| Jun 15, 2022 | Permit Mailed |
| Jun 15, 2022 | Typist for Processing |
| Jun 15, 2022 | Executive Sign Off |
| Jun 15, 2022 | Sent to Photo Copy |
| Jun 15, 2022 | Permit Approved |
| Jul 08, 2022 | Land Evidence Date |
| Jun 07, 2023 | Dock Post-Construction Certification by Engineer received. |