| Action Date | Action Description |
|---|---|
| Jul 01, 2022 | Maintenance Certification Request |
| Jul 07, 2022 | Administrative Review for Completeness |
| Jul 12, 2022 | Eng Team Review for Completeness |
| Jul 19, 2022 | Deficient Application - Owner Notification Sent |
| Jul 22, 2022 | Deficient Application Picked Up |
| Feb 15, 2023 | Deficiency Response Received |
| Feb 23, 2023 | Eng Team Review for Completeness |
| Feb 23, 2023 | Application Accepted |
| Feb 23, 2023 | Project Manager |
| Mar 15, 2023 | HPHC Historical Preservation No Effect |
| Aug 22, 2023 | Engineering Report |
| Aug 24, 2023 | Typist for Processing |
| Aug 24, 2023 | Executive Sign Off |
| Aug 24, 2023 | Sent to Photo Copy |
| Aug 24, 2023 | Permit Approved |
| Aug 29, 2023 | Permit Mailed |
| Sep 27, 2023 | Land Evidence Date |
| Oct 15, 2024 | Commencement of Work Notice received |