| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| Sep 21, 2022 | Buffer Zone Management Application Received |
| Sep 26, 2022 | Administrative Review for Completeness |
| Sep 27, 2022 | HPHC Historical Preservation No Effect |
| Sep 28, 2022 | Bio Team Review for Completeness |
| Sep 28, 2022 | Application Accepted |
| Oct 03, 2022 | Project Manager |
| Dec 14, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jan 09, 2023 | Additional Information Received |
| Apr 26, 2023 | Biologist Report |
| May 01, 2023 | Typist for Processing |
| May 01, 2023 | Executive Sign Off |
| May 01, 2023 | Sent to Photo Copy |
| May 01, 2023 | Permit Approved |
| May 10, 2023 | Permit Mailed |
| May 15, 2023 | Land Evidence Date |
| Jun 12, 2023 | Commencement of Work Notice received |
| Jun 18, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Jun 28, 2024 | Monitoring Report |
| Jun 28, 2024 | Assent Requirement |
| Aug 05, 2024 | Note to File |