| Action Date | Action Description |
|---|---|
| Nov 09, 2022 | Assent Application Received |
| Nov 15, 2022 | Administrative Review for Completeness |
| Nov 29, 2022 | Eng Team Review for Completeness |
| Nov 29, 2022 | Application Accepted |
| Jan 10, 2023 | HPHC Historical Preservation No Effect |
| Feb 16, 2023 | Plans Received |
| Feb 21, 2023 | Engineering Report |
| Mar 02, 2023 | Typist for Processing |
| Mar 02, 2023 | Executive Sign Off |
| Mar 02, 2023 | Sent to Photo Copy |
| Mar 02, 2023 | Permit Approved |
| Mar 08, 2023 | Permit Mailed |
| Apr 03, 2023 | Land Evidence Date |