| Action Date | Action Description |
|---|---|
| Sep 18, 2023 | Assent Application Received |
| Sep 22, 2023 | Administrative Review for Completeness |
| Oct 06, 2023 | Bio Team Review for Completeness |
| Oct 06, 2023 | Application Accepted |
| Oct 06, 2023 | Project Manager |
| Oct 17, 2023 | HPHC Historical Preservation No Effect |
| Feb 05, 2024 | Additional Information Requested from Applicant |
| Feb 19, 2024 | Correspondence Received |
| Apr 15, 2024 | Plans Received |
| Aug 14, 2024 | Biologist Report |
| Aug 15, 2024 | Typist for Processing |
| Aug 15, 2024 | Executive Sign Off |
| Aug 15, 2024 | Sent to Photo Copy |
| Aug 15, 2024 | Permit Approved |
| Aug 16, 2024 | Permit Mailed |
| Aug 22, 2024 | Land Evidence Date |
| Nov 15, 2024 | Additional Information Received |