| Action Date | Action Description |
|---|---|
| Mar 05, 2004 | Application Accepted |
| Mar 17, 2004 | Historical Preservation Approval Granted |
| Jun 01, 2004 | Biologist Report |
| Jun 01, 2004 | Engineering Report |
| Jun 03, 2004 | Permit Approved |
| Jun 03, 2004 | Land Evidence Date |
| Jun 30, 2004 | Correspondence Received |
| Dec 22, 2004 | Modification Request |
| Dec 23, 2004 | Administrative Review for Completeness |
| Mar 01, 2005 | Plans Received |
| Mar 10, 2005 | Team Review for Completeness |
| Apr 15, 2005 | Historical Preservation Approval Granted |
| May 24, 2005 | Engineering Report |
| May 25, 2005 | Typist for Processing |
| May 25, 2005 | Modification Approved |
| May 26, 2005 | Executive Sign Off |
| May 26, 2005 | Sent to Photo Copy |
| Jul 21, 2005 | Assent Correction Mailed |
| Jul 22, 2005 | Land Evidence Date |