| Action Date | Action Description |
|---|---|
| Sep 14, 2021 | Assent Application Received |
| Sep 17, 2021 | Administrative Review for Completeness |
| Sep 28, 2021 | Eng Team Review for Completeness |
| Sep 28, 2021 | Project Manager |
| Sep 28, 2021 | Application Accepted |
| Sep 28, 2021 | Engineering Report |
| Oct 27, 2021 | Typist for Processing |
| Oct 27, 2021 | Executive Sign Off |
| Oct 27, 2021 | Permit Approved |
| Oct 28, 2021 | Permit Mailed |
| Nov 02, 2021 | Land Evidence Date |