| Action Date | Action Description |
|---|---|
| Nov 10, 2022 | Maintenance Certification Request |
| Nov 16, 2022 | Administrative Review for Completeness |
| Nov 30, 2022 | Eng Team Review for Completeness |
| Nov 30, 2022 | Deficient Application - Owner Notification Sent |
| Dec 28, 2022 | Deficient Application Picked Up |
| Feb 20, 2023 | Deficiency Response Received |
| Mar 07, 2023 | Eng Team Review for Completeness |
| Mar 07, 2023 | Deficient Application - Owner Notification Sent |
| Mar 24, 2023 | Deficiency Response Received |
| Mar 27, 2023 | Eng Team Review for Completeness |
| Mar 27, 2023 | Application Accepted |
| Mar 27, 2023 | Permit Approved |
| Mar 28, 2023 | Permit Mailed |