| Action Date | Action Description |
|---|---|
| Jul 08, 2005 | Maintenance Certification Request |
| Jul 11, 2005 | Administrative Review for Completeness |
| Jul 14, 2005 | Team Review for Completeness |
| Jul 14, 2005 | Application Accepted |
| Jul 21, 2005 | HPHC Review Pending |
| Jul 28, 2005 | Plans Received |
| Aug 10, 2005 | Engineering Report |
| Aug 12, 2005 | Typist for Processing |
| Aug 12, 2005 | Executive Sign Off |
| Aug 12, 2005 | Sent to Photo Copy |
| Aug 16, 2005 | Permit Approved |
| Sep 09, 2005 | Land Evidence Date |
| Apr 26, 2006 | Commencement of Work Notice received |