| Action Date | Action Description | 
|---|---|
| Feb 16, 2023 | Maintenance Certification Request | 
| Feb 22, 2023 | Administrative Review for Completeness | 
| Feb 23, 2023 | Eng Team Review for Completeness | 
| Feb 23, 2023 | Bio Team Review for Completeness | 
| Feb 23, 2023 | Application Accepted | 
| Feb 23, 2023 | Project Manager | 
| Mar 06, 2023 | Plans Received | 
| Mar 08, 2023 | HPHC Historical Preservation No Effect | 
| Mar 10, 2023 | Biologist Report | 
| Mar 27, 2023 | Typist for Processing | 
| Mar 27, 2023 | Executive Sign Off | 
| Mar 27, 2023 | Sent to Photo Copy | 
| Mar 27, 2023 | Permit Approved | 
| Mar 30, 2023 | Permit Mailed | 
| Apr 18, 2023 | Land Evidence Date | 
| May 22, 2023 | Commencement of Work Notice received |