| Action Date | Action Description | 
|---|---|
| Oct 30, 2003 | ISDS Approved | 
| Mar 25, 2004 | Application Accepted | 
| Mar 30, 2004 | Biologist Report | 
| Mar 30, 2004 | Engineering Report | 
| Mar 31, 2004 | Permit Approved | 
| Mar 31, 2004 | Land Evidence Date | 
| Apr 09, 2004 | Historical Preservation Approval Granted | 
| Jun 17, 2005 | Modification Request | 
| Jun 20, 2005 | Administrative Review for Completeness | 
| Jun 21, 2005 | Team Review for Completeness | 
| Jun 27, 2005 | Biologist Report | 
| Jun 27, 2005 | Engineering Report | 
| Jul 01, 2005 | Typist for Processing | 
| Jul 01, 2005 | Executive Sign Off | 
| Jul 01, 2005 | Sent to Photo Copy | 
| Jul 05, 2005 | Modification Approved | 
| Jul 21, 2005 | Historical Preservation Approval Granted | 
| Jul 27, 2005 | Land Evidence Date |