| Action Date | Action Description | 
|---|---|
| Mar 29, 2004 | Application Accepted | 
| Apr 13, 2004 | Engineering Report | 
| Apr 14, 2004 | Permit Approved | 
| Apr 14, 2004 | Land Evidence Date | 
| Jul 22, 2024 | Modification Request | 
| Jul 24, 2024 | Administrative Review for Completeness | 
| Aug 01, 2024 | Additional Information Received | 
| Aug 02, 2024 | Bio Team Review for Completeness | 
| Aug 20, 2024 | Application Accepted | 
| Aug 20, 2024 | Project Manager | 
| Sep 13, 2024 | HPHC Historical Preservation No Effect | 
| Oct 07, 2024 | Additional Information Received | 
| Nov 19, 2024 | Plans Received | 
| Jan 13, 2025 | Plans Received | 
| Feb 24, 2025 | Additional Information Received | 
| Mar 06, 2025 | US Army Corps of Engineers Project Number received. | 
| Mar 25, 2025 | Additional Information Received | 
| May 01, 2025 | Plans Received | 
| May 30, 2025 | Plans Received | 
| Jun 03, 2025 | 30 day Public Notice Issued | 
| Jul 03, 2025 | Public Notice End Date | 
| Jul 16, 2025 | Dock Meeting -- Approval | 
| Aug 03, 2025 | Public Notice End Date Extension Granted | 
| Aug 08, 2025 | Biologist Report | 
| Aug 15, 2025 | Typist for Processing | 
| Aug 15, 2025 | Executive Sign Off | 
| Aug 15, 2025 | Sent to Photo Copy | 
| Aug 15, 2025 | Modification Approved | 
| Aug 15, 2025 | Modification mailed | 
| Aug 15, 2025 | Executive Sign Off | 
| Aug 15, 2025 | Sent to Photo Copy | 
| Aug 18, 2025 | Correspondence Received | 
| Aug 18, 2025 | Land Evidence Date | 
| Aug 18, 2025 | Permit Mailed | 
| Oct 02, 2025 | Commencement of Work Notice received |