| Action Date | Action Description | 
|---|---|
| Jan 11, 2005 | Assent Application Received | 
| Jan 12, 2005 | Administrative Review for Completeness | 
| Jan 14, 2005 | Team Review for Completeness | 
| Jan 14, 2005 | Application Accepted | 
| Jan 14, 2005 | Category A* (Docks) | 
| Jan 20, 2005 | 30 day Public Notice Issued | 
| Jan 28, 2005 | HPHC Review Pending | 
| Jan 31, 2005 | 30 day Public Notice Issued | 
| Feb 21, 2005 | Dock Subcommittee Meeting Held | 
| Feb 23, 2005 | US Army Corp of Engineers Permit Date | 
| Feb 24, 2005 | US Army Corps of Engineers Approval Received | 
| Feb 25, 2005 | Biologist Report | 
| Feb 25, 2005 | Engineering Report | 
| Mar 01, 2005 | Executive Sign Off | 
| Mar 02, 2005 | Public Notice End Date | 
| May 03, 2005 | Ready to Schedule Semi-Monthly Meeting | 
| May 03, 2005 | Mail Agenda Notice | 
| May 10, 2005 | Semi-Monthly Meeting Held | 
| May 10, 2005 | Council Approval Granted | 
| May 10, 2005 | Semi-Monthly Meeting Date Scheduled | 
| May 16, 2005 | Stipulation Package from Biologist | 
| May 16, 2005 | Stipulation Package by Engineer | 
| May 18, 2005 | Typist for Processing | 
| May 18, 2005 | Executive Sign Off | 
| May 18, 2005 | Sent to Photo Copy | 
| May 18, 2005 | Permit Approved | 
| Jun 02, 2005 | Land Evidence Date | 
| Sep 19, 2005 | Biologist Report | 
| Sep 19, 2005 | Executive Sign Off | 
| Sep 19, 2005 | Legal Response/Decision |