| Action Date | Action Description | 
|---|---|
| Dec 12, 2006 | Assent Application Received | 
| Dec 13, 2006 | Administrative Review for Completeness | 
| Dec 13, 2006 | Team Review for Completeness | 
| Dec 13, 2006 | Team Review for Completeness | 
| Dec 13, 2006 | Application Accepted | 
| Dec 13, 2006 | Category A* (Docks) | 
| Dec 18, 2006 | 30 day Public Notice Issued | 
| Jan 18, 2007 | Public Notice End Date | 
| Feb 14, 2007 | Plans Received | 
| Feb 15, 2007 | Typist for Processing | 
| Feb 15, 2007 | Executive Sign Off | 
| Feb 15, 2007 | Sent to Photo Copy | 
| Feb 15, 2007 | Biologist Report | 
| Feb 15, 2007 | Engineering Report | 
| Feb 15, 2007 | Permit Approved | 
| Mar 22, 2007 | US Army Corp of Engineers Permit Date | 
| Mar 26, 2007 | US Army Corps of Engineers Approval Received | 
| Jul 20, 2007 | Land Evidence Date |