| Action Date | Action Description | 
|---|---|
| Mar 03, 2008 | Assent Application Received | 
| Mar 04, 2008 | Administrative Review for Completeness | 
| Mar 10, 2008 | Deficient Application - Owner Notification Sent | 
| Mar 13, 2008 | Deficient Application Picked Up | 
| Mar 14, 2008 | Deficiency Response Received | 
| Mar 18, 2008 | Entry of Appearance Received | 
| Mar 19, 2008 | Administrative Review for Completeness | 
| Mar 19, 2008 | Team Review for Completeness | 
| Mar 19, 2008 | Application Accepted | 
| Apr 30, 2008 | HPHC Historical Preservation No Effect | 
| Jun 12, 2008 | Additional Information Received | 
| Jun 20, 2008 | Plans Received | 
| Jun 26, 2008 | Biologist Report | 
| Jun 26, 2008 | Engineering Report | 
| Jul 01, 2008 | Additional Information Received | 
| Jul 02, 2008 | Typist for Processing | 
| Jul 02, 2008 | Executive Sign Off | 
| Jul 02, 2008 | Sent to Photo Copy | 
| Jul 02, 2008 | Permit Approved | 
| Jul 03, 2008 | Land Evidence Date | 
| Jul 15, 2008 | Commencement of Work Notice received | 
| Apr 26, 2011 | Extension of Permit Request | 
| Jan 25, 2013 | Correspondence Mailed/Faxed/E-mailed | 
| Feb 06, 2013 | Certified Receipt Received | 
| Sep 01, 2020 | Correspondence Mailed/Faxed/E-mailed |