| Action Date | Action Description | 
|---|---|
| Jan 29, 2010 | Assent Application Received | 
| Feb 01, 2010 | Administrative Review for Completeness | 
| Feb 02, 2010 | Team Review for Completeness | 
| Feb 12, 2010 | Team Review for Completeness | 
| Feb 16, 2010 | Deficient Application - Owner Notification Sent | 
| Mar 08, 2010 | Deficiency Response Received | 
| Mar 16, 2010 | Team Review for Completeness | 
| Mar 16, 2010 | Team Review for Completeness | 
| Mar 16, 2010 | Application Accepted | 
| Apr 16, 2010 | HPHC Historical Preservation No Effect | 
| Apr 30, 2010 | Additional Information Received | 
| May 04, 2010 | Engineering Report | 
| May 05, 2010 | Biologist Report | 
| May 07, 2010 | Permit Approved | 
| May 28, 2010 | Land Evidence Date |