| Action Date | Action Description | 
|---|---|
| May 19, 2011 | Assent Application Received | 
| May 20, 2011 | Administrative Review for Completeness | 
| Jun 13, 2011 | Team Review for Completeness | 
| Jun 13, 2011 | Team Review for Completeness | 
| Jun 13, 2011 | Application Accepted | 
| Jun 21, 2011 | HPHC Historical Preservation No Effect | 
| Jun 30, 2011 | Additional Information Received | 
| Jul 06, 2011 | 30 day Public Notice Issued | 
| Jul 08, 2011 | Plans Received | 
| Aug 06, 2011 | Public Notice End Date | 
| Aug 23, 2011 | Land Evidence Date | 
| Sep 15, 2011 | US Army Corps of Engineers Approval Received | 
| Sep 16, 2011 | Biologist Report | 
| Sep 16, 2011 | Engineering Report | 
| Sep 20, 2011 | Permit Approved | 
| Sep 20, 2011 | Category A* (Docks) | 
| Sep 20, 2011 | Typist for Processing | 
| Sep 21, 2011 | Executive Sign Off | 
| Sep 21, 2011 | Sent to Photo Copy | 
| Oct 03, 2011 | Land Evidence Date | 
| Apr 27, 2012 | Team Review for Completeness |